?《流浪巫师Rogue Wizards》移动版近日开启测试

Sovereign Project | 59110-001

百度 对于存在价格差异的原因,客服表示是由于其中包含苹果收取的手续费。

The proposed project will (i) install a 200 MW/400 MWh of utility-scale BESS at a substation in the north of Phnom Penh to supply ancillary service for stabilizing the transmission grid and improving power quality, avoiding curtailment and (ii) enhance technical and regulatory capacity of EDC for technically and financially sustainable BESS operation. The project will aim at deploying at least 2100 MW / 4100 MWh of BESS capacity with grid-forming inverter in various locations across Cambodia mostly for ancillary services, peak load shifting and grid congestion relief. The total project cost is estimated at $62.1 million, of which $40 million is to be financed with ADB concessional OCR, $20 million from the Green Climate Fund (GCF) through the ASEAN Catalytic Green Finance Facility Green Recovery Program (ACGF GRP) and the remainder through co-financing.

Project Details

Project Name
Utility-Scale Battery Energy Storage Project
Project Number
59110-001
Country / Economy
  • Cambodia
Project Status
Proposed
Project Type / Modality of Assistance
  • Grant
  • Loan
Source of Funding / Amount
Loan: Utility-Scale Battery Energy Storage Project
Source Amount
Concessional ordinary capital resources lending US$ 40.00 million
Sector / Subsector
  • Energy / Electricity transmission and distribution

Gender
Some gender elements
Description
The proposed project will (i) install a 200 MW/400 MWh of utility-scale BESS at a substation in the north of Phnom Penh to supply ancillary service for stabilizing the transmission grid and improving power quality, avoiding curtailment and (ii) enhance technical and regulatory capacity of EDC for technically and financially sustainable BESS operation. The project will aim at deploying at least 2100 MW / 4100 MWh of BESS capacity with grid-forming inverter in various locations across Cambodia mostly for ancillary services, peak load shifting and grid congestion relief. The total project cost is estimated at $62.1 million, of which $40 million is to be financed with ADB concessional OCR, $20 million from the Green Climate Fund (GCF) through the ASEAN Catalytic Green Finance Facility Green Recovery Program (ACGF GRP) and the remainder through co-financing.
Project Rationale and Linkage to Country/Regional Strategy

Cambodia has substantially increased power generation capacity while reducing imports from neighboring countries. Domestic power generation has rapidly increased from 8.68 TWh in 2020 to 17.85 TWh in 2024, while imports decreased from 3.06 TWh in 2020 to 1.57 TWh in 2024. Such a sharp domestic electricity generation increase has been mainly driven by 1,201 megawatts (MW) of renewable energy capacity addition in 20202024. Solar photovoltaic (PV) is the least cost and the fast-growing generation technology in the domestic renewable energy power capacity, which has increased from 105 MW in 2020 to 827 MW in 2024. The government plans to spur further renewable energy capacity, adding up to 31% of installed capacity of solar PV and up to 7% of installed capacity of wind power. By 2030, solar PV and wind power are expected to account for 38% of the total generation capacity in Cambodia. In particular, solar PV is considered critical as it supplements seasonal variability of hydropower outputs between dry and rainy seasons throughout the year in Cambodia.

Further increase in variable renewable energy capacity by 2030, especially solar PV, requires strengthening of the transmission grid system by scaling up battery energy storage systems (BESS), which can provide an ancillary service, peak-shifting, and load smoothing functions to stabilize the transmission grid and evacuate growing renewable electricity. EDC sees cumulative capacity of solar PV will reach 2,000 MW by 2028 and 5,390 MW by 2030. The updated Power Development Master Plan (PDP) 20202040 planned to install 1,100 GW of BESS capacity by 2030 but EDC currently plans to upsize BESS capacity target up to 3,000 MW to support solar power evacuation while stabilizing the transmission grid.

A massive black-out in southern Viet Nam, which was extended to Cambodia in April 2025, also underscored the importance to enhance the grid system in the country for stable power supply. Scaling up BESS is critical for the transmission grid system to withstand the major contingencies such as a sudden loss of interconnection/ transmission line. Electricite du Cambodge (EDC) has been successfully managing the bid for a total of 162.5 MW/300 MWh of BESS procurement with its own funds. It also targets to (i) reach commercial operation of the proposed project by the first quarter of 2027, and (ii) accelerate BESS capacity addition up to 2,000 MW by 2028, to help urgently add BESS capacity for commercial operation by the first quarter of 2027.

Impact

Economic growth enabled through higher integration of renewable energy in the power system

Outcome

TBD

Outputs

TBD

Geographical Location
Nation-wide

Safeguard Categories

Environment
B
Involuntary Resettlement
B
Indigenous Peoples
C

Summary of Environmental and Social Aspects

Environmental Aspects
Involuntary Resettlement
Indigenous Peoples

Stakeholder Communication, Participation, and Consultation

During Project Design
During Project Implementation

Contact

Responsible ADB Officer
Yamamura, Shigeru
Responsible ADB Department
Sectors Department 1
Responsible ADB Division
Energy Sector Office?(SD1-ENE)
Executing Agencies
Electricite Du Cambodge

Timetable

Concept Clearance
01 Feb 2027
Fact Finding
01 Dec 2025 to 12 Dec 2025
MRM
-
Approval
-
Last Review Mission
-
Last PDS Update
30 Jun 2025

Funding

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

None currently available.


Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

None currently available.


Evaluation Documents See also: Independent Evaluation

None currently available.


Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

No tenders for this project were found.

Contracts Awarded

No contracts awarded for this project were found

Procurement Plan

None currently available.